Asset Management
Availability is not a count of what you own
Allocated, checked out, awaiting inspection, under repair. What “available” should actually mean.
A contracts manager needs a scissor lift on the Riverside job tomorrow morning. The plant register says the business owns six. Four are on other sites, one failed its pre-use check this morning with a hydraulic leak, and the sixth is in the yard but due its thorough examination on Friday. On paper the business has six. In practice it has none it can send without a phone call.
This is the gap between ownership and availability. Most asset registers are good at the first and poor at the second.
Owned is not the same as usable
A register of what the business owns answers a finance question. The operational question is different: what can I send, where, and when? Answering it needs the asset's current state, not just its existence.
For plant, tools and equipment in field services, those states are fairly consistent:
- Available: in a known place, inspected, serviceable and not committed to anything
- Allocated: committed to a project and a site, whether or not it has arrived
- Checked out: in the custody of a named person, with an expected return date
- Awaiting inspection: due or overdue a check, and not to be used until it is done
- Under repair: withdrawn after a fault or a failed check, with the repair in hand
- Out of service: not coming back soon, or not coming back at all
Only the first of these is available. Everything else is a reason why the asset in the register is not an asset you can use.
Some of these states are predictable. An inspection due on Friday makes an asset unavailable for next week as surely as a breakdown does, but unlike a breakdown it can be seen coming. A register that shows the next due date alongside the allocation lets someone plan around it rather than find out at the depot.
Why the states drift
States drift for the same reason most records drift: they depend on someone updating them after the event. A lift goes out to a site on a verbal agreement. A breaker passes between two teams without anyone recording the handover. A check fails on site, the operative tags the machine and calls the depot, and the register still shows it as serviceable until someone in the office catches up.
The consequences are practical. Plant is hired in while an owned unit sits idle on a finished job. A machine goes out overdue its inspection. And the one person who knows where everything really is becomes the system, which works until that person is on leave.
Transfers make it worse. Plant moved directly from one site to another, without coming back through the yard, is the hardest kind to track. The register shows it on the first job, the second job's supervisor thinks of it as theirs, and the expected return date belongs to an allocation that has quietly ended.
How do you keep plant availability accurate?
The fix is to make state changes part of the work that causes them, rather than a separate update afterwards. Allocation should be a recorded step, with an asset, a project, a site and an expected return. Handover should name the person and record the condition it went out in. A failed pre-use check should withdraw the asset and open the fault without waiting for the office. Returns should record condition again.
When those steps are recorded where they happen, the availability figure becomes something people can trust: how many units exist, how many are free, what is checked out and to whom, what is due an inspection and what is out of service, by site. That is the number a contracts manager needs at four in the afternoon, and it is the number most registers cannot give.
In Roveya, custody, inspections and faults are recorded against the asset itself. A failed pre-use check completed in Roveya Ops withdraws the asset from availability and opens the fault, while allocation and repair assignment are handled in Roveya Admin. A person still decides where plant goes. The record makes sure they are deciding from the real position.
That matters most on the busy days, when three jobs want the same machine and the decision has to be made quickly. A record that is current turns a round of phone calls into a look at a screen.
Ownership tells you what you paid for. Availability tells you what you can use tomorrow. They are different questions, and they need different records.
Frequently asked questions
What does available mean in a plant register?
An asset is available when it is in a known place, inspected, serviceable and not committed to anything. Assets that are allocated to a project, checked out to a named person, awaiting inspection, under repair or out of service are not available, even though they appear on the register. Availability answers what can be sent, where and when, which an ownership count cannot.
How often does a scissor lift need a thorough examination?
Under LOLER, lifting equipment used to lift people, including scissor lifts and other MEWPs, needs a thorough examination by a competent person at least every six months, or in line with a written scheme of examination. Most other lifting equipment is examined at least every twelve months. Because the due date is known in advance, it should sit alongside allocation so planners can work around it.
What should happen when plant fails a pre-use check?
The asset should be withdrawn from use straight away and a fault opened, without waiting for the office to catch up. If the failure is only reported by phone, the register can keep showing the machine as serviceable and it may be sent out again. Recording the failed check where it happens keeps the availability figure accurate and starts the repair process.
How do you track plant transferred directly between sites?
Record every transfer as a step: the asset, the receiving project and site, the person taking custody, its condition and the expected return. Plant moved directly between sites without passing through the yard is the hardest to track, because the register still shows it on the first job and the original return date belongs to an allocation that has quietly ended.